「110 Hualien County Construction Projects and Noise Inspection and Control Plan」於資料集「EPQSummary_NoiseAndVibration」由單位「行政院環境保護署」的陳先生所提供,聯繫電話是02-2311-7722#2386,最近更新時間為:2023-07-30 01:01:50。 欄位Project Title的內容是110 Hualien County Construction Projects and Noise Inspection and Control Plan , 欄位Project Subject的內容是According to the contract to standardize the work items and content, and in line with the requirements of your bureau, complete the prescribed work items within 2011 and submit a report on the results of the work, and submit the report on the execution results of the previous month at the beginning of each month. Up to now, a total of 54 construction sites have completed the signing of consent for site self-management (38 new sites in the year). In terms of road adoption, there are currently 54 sites (38 new sites in the year) with a cleaning length of 53,383 kilometers. Construction project inspection and inspection A total of 4,700 cases have been completed, and 2,444 cases of air pollution fee collection and reminders (collection / reminders) have been collected, and the number of reminders has reached 88. The rest of the implementation results from January to December are as follows. :
(1) Inspection and control operations
In 2011, a total of 4,476 construction site pollution control inspections were completed, of which 4,281 were missing 0, accounting for about 96%, 179 were missing below 10, accounting for about 4%, and 16 were severely missing above 10, accounting for less than 1%. The most of 14% are the lack of 4 points of the dust-proof net buckle when the material is stacked and the dust net is not completely covered, followed by 12% of the lack of 4 points of the dust-proof net of the structure and 12% of the lack of 4 points of the road pavement in the construction area. At present, there are 7 cases of violations reported with a total amount of fines of 300,000 yuan, all of which have been improved. Compared with the inspection targets set at the beginning of the implementation of this plan, the cumulative achievement rate of inspections in each month has reached 100%. Among them, the number of inspections in each township and city is the largest in Hualien City with 1,125 and Ji'an Township with 1,028, followed by Shoufeng Township with 473 and Xincheng Township with 427. In terms of project categories, 2,496 other projects and 983 construction (RC) projects were the main inspection points.According to the statistics of the number of inspections, there are currently 224 inspections, with 82 other types of projects being the most, followed by 63 construction (RC) projects. According to the statistics on the number of inspection cases in each township, Hualien City with 64 cases and Ji'an Township with 38 cases are the main inspection focus areas.
In order to implement noise control on construction sites, the project personnel have carried out a total of 109 active inspections and measurements of construction site noise in 110 years. The noise measurement is carried out according to the main construction machinery on site, including strange hands, cranes, crushers, and forecasters. Machines and tools that are prone to noise sources, such as mixer trucks, measure Leq and Lmax according to regulations. So far, a total of 19 construction sites have been found to have excessive sound levels during construction. After communicating with the industry to improve and re-examined within the improvement period, there are no cases of exceeding the standard. Statistics of the noise measurement results of the 64 construction sites show that the measurement range of Leq is between 52.5 and 81.2dB(A), and the measurement range of Lmax is between 57.6 and 98.1dB(A). Projects with higher Lmax values are mostly concentrated in excavation and pile arrangement.
(2) Collection of air pollution control fees for construction projects
Statistics on the collection of air pollution prevention and control fees for construction projects in 110 years, a total of 61,862,121 yuan was collected, of which dredging projects collected the most at 29,173,855 yuan, accounting for 47% of the total collection amount, followed by other types of projects... , 欄位Project Year的內容是2021 , 欄位Organizer的內容是Environmental Protection Bureau, Hualien County , 欄位Executive Unit的內容是康廷工程顧問企業有限公司 , 欄位Reporting download URL的內容是https://epq.epa.gov.tw/ProjectDoc/FileDownload?fid=276785&proj_id=1101024040&doc_kind=1 , 欄位Publish Date的內容是20220211 。
Project Title
110 Hualien County Construction Projects and Noise Inspection and Control Plan
Project Subject
According to the contract to standardize the work items and content, and in line with the requirements of your bureau, complete the prescribed work items within 2011 and submit a report on the results of the work, and submit the report on the execution results of the previous month at the beginning of each month. Up to now, a total of 54 construction sites have completed the signing of consent for site self-management (38 new sites in the year). In terms of road adoption, there are currently 54 sites (38 new sites in the year) with a cleaning length of 53,383 kilometers. Construction project inspection and inspection A total of 4,700 cases have been completed, and 2,444 cases of air pollution fee collection and reminders (collection / reminders) have been collected, and the number of reminders has reached 88. The rest of the implementation results from January to December are as follows. : (1) Inspection and control operations In 2011, a total of 4,476 construction site pollution control inspections were completed, of which 4,281 were missing 0, accounting for about 96%, 179 were missing below 10, accounting for about 4%, and 16 were severely missing above 10, accounting for less than 1%. The most of 14% are the lack of 4 points of the dust-proof net buckle when the material is stacked and the dust net is not completely covered, followed by 12% of the lack of 4 points of the dust-proof net of the structure and 12% of the lack of 4 points of the road pavement in the construction area. At present, there are 7 cases of violations reported with a total amount of fines of 300,000 yuan, all of which have been improved. Compared with the inspection targets set at the beginning of the implementation of this plan, the cumulative achievement rate of inspections in each month has reached 100%. Among them, the number of inspections in each township and city is the largest in Hualien City with 1,125 and Ji'an Township with 1,028, followed by Shoufeng Township with 473 and Xincheng Township with 427. In terms of project categories, 2,496 other projects and 983 construction (RC) projects were the main inspection points.According to the statistics of the number of inspections, there are currently 224 inspections, with 82 other types of projects being the most, followed by 63 construction (RC) projects. According to the statistics on the number of inspection cases in each township, Hualien City with 64 cases and Ji'an Township with 38 cases are the main inspection focus areas. In order to implement noise control on construction sites, the project personnel have carried out a total of 109 active inspections and measurements of construction site noise in 110 years. The noise measurement is carried out according to the main construction machinery on site, including strange hands, cranes, crushers, and forecasters. Machines and tools that are prone to noise sources, such as mixer trucks, measure Leq and Lmax according to regulations. So far, a total of 19 construction sites have been found to have excessive sound levels during construction. After communicating with the industry to improve and re-examined within the improvement period, there are no cases of exceeding the standard. Statistics of the noise measurement results of the 64 construction sites show that the measurement range of Leq is between 52.5 and 81.2dB(A), and the measurement range of Lmax is between 57.6 and 98.1dB(A). Projects with higher Lmax values are mostly concentrated in excavation and pile arrangement. (2) Collection of air pollution control fees for construction projects Statistics on the collection of air pollution prevention and control fees for construction projects in 110 years, a total of 61,862,121 yuan was collected, of which dredging projects collected the most at 29,173,855 yuan, accounting for 47% of the total collection amount, followed by other types of projects...
Project Year
2021
Organizer
Environmental Protection Bureau, Hualien County
Executive Unit
康廷工程顧問企業有限公司
Reporting download URL
https://epq.epa.gov.tw/ProjectDoc/FileDownload?fid=276785&proj_id=1101024040&doc_kind=1
Publish Date
20220211
「110 Hualien County Construction Projects and Noise Inspection and Control Plan」所屬的資料集:「EPQSummary_NoiseAndVibration」的其他資料
Project Title:
Project Subject:
The main work items of this project included: assisting the EPA (Environmental Protection Administra
Project Year:
2014
Organizer:
Department of Air Quality Protection & Noise Control
Project Title:
Development of underwater noise investigation technology for offshore wind power facilities.
Project Subject:
In recent years, the government has been dedicated to the development of green industry (including r
Project Year:
2018
Organizer:
Project Title:
The project of strengthen repeatedly noise cases complaint inspection and low frequency noise contro
Project Subject:
The noise is one of the major cases environmental pollutions. The number of noise complaint were app
Project Year:
2018
Organizer:
Department of Air Quality Protection & Noise Control
Project Title:
""
Project Subject:
"According to the statistics from Establishing Public Nuisance Petitions Processing Procedures of En
Project Year:
2015
Organizer:
"Environmental Protection Bureau, Chiayi City"
Project Title:
Noise behaviors and Aviation Noise Control Project
Project Subject:
Since there is still much room for improvement regarding the performance of aviation noise monitorin
Project Year:
2013
Organizer:
Department of Air Quality Protection & Noise Control
Project Title:
Research on the measurement of low-frequency non-ionizing radiation and the calibration of monitorin
Project Subject:
In order to ensure the accuracy and reliability of long-term monitoring data, this plan conducts res
Project Year:
2017
Organizer:
Department of Air Quality Protection & Noise Control
Project Title:
2016 Noise monitoring and management plan in Tainan city
Project Subject:
This project focused on the noise pollution is principally categorized into nine parts: 1) to comple
Project Year:
2016
Organizer:
Environmental Protection Bureau of Tainan City
Project Title:
The Impact of Electromagnetic Field (EMF) on the Environment Project
Project Subject:
The objectives of this project include: to collect analyze the latest international information on n
Project Year:
2011
Organizer:
Department of Air Quality Protection & Noise Control
Project Title:
Noise behaviors and Aviation Noise Control Project
Project Subject:
Through the implementation of this project, it is hoped to understand the current situation and tren
Project Year:
2015
Organizer:
Department of Air Quality Protection & Noise Control
Project Title:
Project Subject:
Pursuant to the project contract, this project was implemented from July 8, 2010 to December 31, 201
Project Year:
2010
Organizer:
Environmental Protection Bureau of Tainan City
Project Title:
2009 Air quality management development plan、Control project of escape pollution source and dinging
Project Subject:
Penghu 『2009 The air quality management development plan』 and 『2009 The control project of escape po
Project Year:
2009
Organizer:
Environmental Protection Bureau, Penghu County
Project Title:
The control strategy of the in-use vehicle noise
Project Subject:
This project assisted the EPA to operate and maintain the in-use vehicle noise reporting website sys
Project Year:
2015
Organizer:
Department of Air Quality Protection & Noise Control
Project Title:
Investigation of environmental low-frequency noise and vibration and research projet for improvement
Project Subject:
The number of people affected by noise and vibration are increased by the days, and the quality of l
Project Year:
2015
Organizer:
Department of Air Quality Protection & Noise Control
Project Title:
Non-ionizing radiation - emission source selected and the advocacy of the National Geographic Inform
Project Subject:
The goal of this project was focused on the measurement and analysis of non-ionization radiation emi
Project Year:
2012
Organizer:
Department of Air Quality Protection & Noise Control
Project Title:
Research on Noise Control and Assessment with Detection Camera System Applied to In-use Motor Vehicl
Project Subject:
Among the petitions submitted in recent years, many have been complaining against the big noise made
Project Year:
2018
Organizer:
Department of Air Quality Protection & Noise Control
Project Title:
106 Hualien County construction inspection cum noise control, general noise delineation program
Project Subject:
According to the contractual norms work items and contents, in accordance with the requirements of y
Project Year:
2017
Organizer:
Environmental Protection Bureau, Hualien County
Project Title:
Control measures for in-using motor vehicle’s noise and for prone to noise emission facilities
Project Subject:
This project assisted the EPA to operate and maintain the in-use vehicles noise reporting website sy
Project Year:
2014
Organizer:
Department of Air Quality Protection & Noise Control
Project Title:
The study of traffic and environmental noise control and improvable measures
Project Subject:
This study collected and reviewed the measurement results of traffic and environmental noise from en
Project Year:
2011
Organizer:
Department of Air Quality Protection & Noise Control
Project Title:
Implement of the new vehicle type approval with regard to noise, the new vehicle spot check and the
Project Subject:
This project aims to assist EPA in examination of noise certificates for new vehicle types and all a
Project Year:
2017
Organizer:
Department of Air Quality Protection & Noise Control
Project Title:
The Expansion Project of Environmental Public Nuisance of Pollution Prevention with Nighttime Inspe
Project Subject:
Environmental Protection Bureau, Chiayi City (CYCEPB) has set up the 24 hours Environmental Public N
Project Year:
2022
Organizer:
Environmental Protection Bureau, Chiayi City
Project Title:
Noise Pollution Inspection on Public sentiment and Control Plan for 2019
Project Subject:
This project has been executed since Jan.,2019, including motor vehicle noise control, traffic noise
Project Year:
2019
Organizer:
Environmental Protection Bureau, Taichung City
Project Title:
2013 Taichung City Motorcycle Emission Inspection Station Management Project.
Project Subject:
“2013 Taichung City motorcycle Emission Inspection Station Management Project” had begun from Feb.-0
Project Year:
2013
Organizer:
Environmental Protection Bureau, Taichung City
Project Title:
The Noise Control Management Information System and Noise Control Information Web Update and Mainten
Project Subject:
The goals of this project included system maintenance and data collection of “The Noise Control Mana
Project Year:
2012
Organizer:
Department of Air Quality Protection & Noise Control
Project Title:
Chiayi City Diesel Vehicle Air Pollution Control and Idling Motor Vehicle Park and Stop audit plan i
Project Subject:
As diesel engine has high output horsepower, it consumes relatively less fuel comparing with petrol
Project Year:
2020
Organizer:
Environmental Protection Bureau, Chiayi City
Project Title:
"A project for traffic noise control"
Project Subject:
"As urban developments are getting better everyday, so are transportation systems that are getting m
Project Year:
2014
Organizer:
"Department of Air Quality Protection & Noise Control"
Project Title:
2009 Taoyuan area Air noise monitoring, analysis and promotion
Project Subject:
This plan, according to the goal of the plan and demand for the working project, the groundwork cont
Project Year:
2009
Organizer:
Taoyuan County Government Environment Protection Bureau
Project Title:
Motor vehicles emission testing institutions checking project of 2019
Project Subject:
The project was in accordance with「Regulations Governing Motor Vehicle Air Pollutant and Noise Emiss
Project Year:
2019
Organizer:
Project Title:
"Control measures for in-using motor vehicle’s noise and for prone to noise emission facilities"
Project Subject:
"This project assisted the EPA to operate and maintain the in-use vehicles noise reporting website s
Project Year:
2014
Organizer:
"Department of Air Quality Protection & Noise Control"
Project Title:
Quality monitoring for Motor Vehicle Air Pollution and Noise Emission Testing Organizations.
Project Subject:
This project was commissioned by the National Institute of Environmental Analysis, Environmental Pro
Project Year:
2017
Organizer:
"TBD"2016"TBD"
Project Title:
"TBD"
Project Subject:
"TBD"
Project Year:
2016
Organizer:
"Department of Environmental Protection, Taipei City Government"
行政院環境保護署 的其他資料集
通過逐車審驗運送車輛
每月更新更新,100林先生 | 02-2325-7399#55232 | 2022-01-14 01:25:47
行政院環境保護署包裝及盛裝飲用水水源水質抽驗資料
不定期更新更新,121黃先生 | 02-23117722-2881 | 2022-01-15 01:10:28
行政院環境保護署環境教育機構認證申請書
不定期更新更新,57盧小姐 | (03)4020789分機606 | 2023-08-09 01:05:26
行政院環境保護署光化測站(臺南)小時值資料
不定期更新更新,108陳先生 | 02-2311-7722#2386 | 2023-08-07 01:03:35
行政院環境保護署病媒防治業許可執照資料
每3月更新,104薛先生 | 02-2325-7399#55413 | 2023-07-27 01:02:57
行政院環境保護署
公民營廢棄物清除機構資料
每月更新更新,138何先生 | 02-2311-7722#2653 | 2022-01-14 01:26:25
行政院環境保護署焚化廠基本資料
每月更新更新,49吳先生 | 04-22521718#53526 | 2022-01-15 01:15:18
行政院環境保護署空氣品質小時值_新竹縣_湖口站
每1時更新,88陳先生 | 02-2311-7722#2386 | 2023-08-02 00:58:05
行政院環境保護署空氣品質小時值_雲林縣_斗六站
每1時更新,103陳先生 | 02-2311-7722#2386 | 2023-08-02 00:57:53
行政院環境保護署區域性地下水水質測站位置圖
不定期更新更新,52陳先生 | 02-2311-7722#2386 | 2023-08-07 01:04:32
行政院環境保護署
一般廢棄物清理情況資料
不定期更新更新,84王先生 | (04)2252-1718#53524 | 2023-08-07 01:02:09
行政院環境保護署空氣品質小時值_屏東縣_屏東站
每1時更新,92陳先生 | 02-2311-7722#2386 | 2023-08-02 00:57:36
行政院環境保護署空氣品質小時值_桃園市_桃園站
每1時更新,107陳先生 | 02-2311-7722#2386 | 2023-08-02 00:58:09
行政院環境保護署空氣品質小時值_新北市_萬里站
每1時更新,85陳先生 | 02-2311-7722#2386 | 2023-08-02 00:58:21
行政院環境保護署清潔人員執行職務死亡濟助申請程序
半年更新,40陳小姐 | (04)2252-1718#5358 | 2022-01-14 01:18:01
行政院環境保護署
經過飲用水水源水質保護區之環境影響評估報告書
每2月更新,54黃先生 | 02-23117722#2748 | 2023-08-05 01:00:58
行政院環境保護署紫外線即時監測資料
每1時更新,243陳先生 | 02-2311-7722#2386 | 2023-08-02 00:57:05
行政院環境保護署空氣品質小時值_臺東縣_臺東站
每1時更新,180陳先生 | 02-2311-7722#2386 | 2023-08-02 00:57:34
行政院環境保護署EPQSummary_EnvironmentalEducation
不定期更新更新,180郭先生 | 02-2311-7722 EXT.2399 | 2022-01-15 01:14:02
行政院環境保護署建檔公廁明細-新北市
不定期更新更新,121賴先生 | 04-2252-1718#53686 | 2023-07-27 01:02:01
行政院環境保護署
廢棄物質最終處置資訊網會議資料
每月更新更新,34許先生 | 02-2311-7722#2641 | 2022-01-14 01:24:13
行政院環境保護署0800資源回收免費專線-查詢廢輪胎、鉛蓄電池統計
每年更新更新,52莊先生 | 02-23705888#3108 | 2022-01-14 01:24:27
行政院環境保護署屏東縣水量水質自動監測連線傳輸監測紀錄值即時資料集
不定期更新更新,45許先生 | 02-2311-7722#2831 | 2022-01-18 01:24:51
行政院環境保護署空氣品質小時值_金門縣_金門站
每1時更新,148陳先生 | 02-2311-7722#2386 | 2023-08-02 00:57:23
行政院環境保護署環境科技論壇論文集
每1年更新,35賀先生 | 23117722#2981 | 2023-08-06 01:06:11
行政院環境保護署
應回收廢棄物(廢照明光源類)回收量資料
每年更新更新,49廖小姐 | 02-2370-5888#3103 | 2022-01-14 01:24:39
行政院環境保護署空氣品質小時值_花蓮縣_花蓮站
每小時更新更新,96謝小姐 | 02-2311-7722#2386 | 2022-01-14 01:04:36
行政院環境保護署特殊性工業區品保品管後監測值資料檔(氣象監測項目)
每年更新更新,137丁先生 | 02-2371-2121#6101 | 2022-01-15 01:07:02
行政院環境保護署空氣品質指標(AQI)概況
每月更新更新,108謝小姐 | 02-23117722#2103 | 2022-01-14 01:20:51
行政院環境保護署行政院環境保護署單位預算案
每年更新更新,32方先生 | 02-2311-7722#2153 | 2022-01-15 01:09:45
行政院環境保護署