Inventory of Heavy Metal Emission from Stationary Source, the Ev
「Inventory of Heavy Metal Emission from Stationary Source, the Ev」於資料集「EPQSummary_ChemicalSubstanceManagement」由單位「行政院環境保護署」的陳先生所提供,聯繫電話是02-2311-7722#2386,最近更新時間為:2023-07-30 01:01:48。 欄位Project Title的內容是Inventory of Heavy Metal Emission from Stationary Source, the Evaluation of Control Technology and the Strategies of Management and Reduction of Heavy Metals. , 欄位Project Subject的內容是In this project, we implemented the emission inventory of heavy metals (Pb, Cd, Hg and As) for the coal-fired power plants, cement kilns, sinter plants and electric arc furnace. Besides, arsenic emission inventory from the semiconductor plants was also done. We have finished the emission factors, emission inventories and risk assessment of heavy metal. We also evaluated the mercury distribution and collected the method for the reduction of heavy metal.
Based on the sampling databases of the Taiwan EPA, we found the main heavy metal emission sources are cement kilns, municipal solid waste incinerator, electric arc furnace and coal-fired power plant.
We also investigated and analyzed the distribution of mercury for a coal-fired power plant, cement kiln and electric arc furnace. We found that mercury mass balance was about 95.7 % and 97.2 percent of mercury was from the coals for coal-fired power plant. After all the coal was burned, 63.8 percent of the mercury was in the fly ash. For the electric arc furnace, mercury mass balance was about 164.5 % and the main mercury source was from the steel scraps (59.8%) and alloy materials (31.9%). 82.9 percent of the mercury was in the fly ash after melting. The mercury mass balance for the cement kiln was only 53.5%. 75.6 percent of the mercury was from the limestone. Most of the mercury will be in the cement product.
The results of the risk assessment of heavy metals for the stationary pollution source indicated that carcinogenic risks and non-carcinogenic risks of the heavy metal were both lower than the standard of health risk 10-6 except the Hoping power plant (1.13×10-6) and Hoping cement kiln plant (1.75×10-6). It may be attributed the fact that the emission concentrations of arsenic were higher. Due to the sampling data was few; heavy metal sampling is necessary in the future. Besides, we have collected the strategies of management and control of heavy metals by other countries and finished the draft of the mercury emission limit for the coal-fired power plant and then gave Taiwan Environmental Protection Administration (EPA) the suggestion of the related policy. , 欄位Project Year的內容是2005 , 欄位Organizer的內容是Department of Air Quality Protection & Noise Control , 欄位Executive Unit的內容是工業技術研究院 黃志峰 , 欄位Reporting download URL的內容是https://epq.epa.gov.tw/ProjectDoc/FileDownload?fid=4606&proj_id=A000000360358&doc_kind=1 , 欄位Publish Date的內容是20061001 。
Project Title
Inventory of Heavy Metal Emission from Stationary Source, the Evaluation of Control Technology and the Strategies of Management and Reduction of Heavy Metals.
Project Subject
In this project, we implemented the emission inventory of heavy metals (Pb, Cd, Hg and As) for the coal-fired power plants, cement kilns, sinter plants and electric arc furnace. Besides, arsenic emission inventory from the semiconductor plants was also done. We have finished the emission factors, emission inventories and risk assessment of heavy metal. We also evaluated the mercury distribution and collected the method for the reduction of heavy metal. Based on the sampling databases of the Taiwan EPA, we found the main heavy metal emission sources are cement kilns, municipal solid waste incinerator, electric arc furnace and coal-fired power plant. We also investigated and analyzed the distribution of mercury for a coal-fired power plant, cement kiln and electric arc furnace. We found that mercury mass balance was about 95.7 % and 97.2 percent of mercury was from the coals for coal-fired power plant. After all the coal was burned, 63.8 percent of the mercury was in the fly ash. For the electric arc furnace, mercury mass balance was about 164.5 % and the main mercury source was from the steel scraps (59.8%) and alloy materials (31.9%). 82.9 percent of the mercury was in the fly ash after melting. The mercury mass balance for the cement kiln was only 53.5%. 75.6 percent of the mercury was from the limestone. Most of the mercury will be in the cement product. The results of the risk assessment of heavy metals for the stationary pollution source indicated that carcinogenic risks and non-carcinogenic risks of the heavy metal were both lower than the standard of health risk 10-6 except the Hoping power plant (1.13×10-6) and Hoping cement kiln plant (1.75×10-6). It may be attributed the fact that the emission concentrations of arsenic were higher. Due to the sampling data was few; heavy metal sampling is necessary in the future. Besides, we have collected the strategies of management and control of heavy metals by other countries and finished the draft of the mercury emission limit for the coal-fired power plant and then gave Taiwan Environmental Protection Administration (EPA) the suggestion of the related policy.
Project Year
2005
Organizer
Department of Air Quality Protection & Noise Control
Executive Unit
工業技術研究院 黃志峰
Reporting download URL
https://epq.epa.gov.tw/ProjectDoc/FileDownload?fid=4606&proj_id=A000000360358&doc_kind=1
Publish Date
20061001
「Inventory of Heavy Metal Emission from Stationary Source, the Ev」所屬的資料集:「EPQSummary_ChemicalSubstanceManagement」的其他資料
Project Title:
Total capacity control planning
Project Subject:
This is a policy implementation project in compliance with the latest Amendment of Air Pollution Con
Project Year:
2002
Organizer:
Department of Air Quality Protection & Noise Control
Project Title:
Promote fluorinated gases emission reduction
Project Subject:
The requirements for the management of high green house potential gases(PFCs, HFCs and SF6) has grad
Project Year:
2005
Organizer:
Department of Air Quality Protection & Noise Control
Project Title:
The Project of promotion of ENERGYSTAR Label
Project Subject:
As 35% of the greenhouse gas emissions can be attributed to the generation of electricity, together
Project Year:
2003
Organizer:
Department of Air Quality Protection & Noise Control
Project Title:
"Project for constructing a safe and comfortable homeland : The plan for the setup of northern envir
Project Subject:
"The purpose of this project is to establish and maintain 3 specialist teams in responding environme
Project Year:
2019
Organizer:
"Toxic and Chemical Substances Bureau"
Project Title:
The Project for Inventory, Analysis, and Application of the Information on Existing Chemical Substan
Project Subject:
Responding to implementation of the regulations of existing chemical substances standard registratio
Project Year:
2020
Organizer:
Toxic and Chemical Substances Bureau
Project Title:
The project of Reviewing Stationary Sources Air Pollution Control Enforcement, Planning Control Stra
Project Subject:
This project supports EPA in implementing and amending/revising the management system of stationary
Project Year:
2004
Organizer:
Department of Air Quality Protection & Noise Control
Project Title:
Applying the Internet of Things to improve chemical substances management, 2019
Project Subject:
The main implementation contents of this project have three aspects for guiding companies this year:
Project Year:
2019
Organizer:
Toxic and Chemical Substances Bureau
Project Title:
Implementing Kaoping airbasin Cap & Trade System and Control Strategy Analysis for Fine Particulate
Project Subject:
There are three major work items within this project - (1) to Promote Cap and Trade pilot program, (
Project Year:
2006
Organizer:
Department of Air Quality Protection & Noise Control
Project Title:
Examine, analyze and supervise in air pollution control fee of stationary pollution source
Project Subject:
In order to realize the pollution to pay fee the social just principle, and by the economical induce
Project Year:
2004
Organizer:
Department of Air Quality Protection & Noise Control
Project Title:
"Project for constructing a safety chemistry homeland : The plan for the setup of northern environme
Project Subject:
"The purpose of this project is to establish and maintain 4 specialist teams in responding environme
Project Year:
2020
Organizer:
"Toxic and Chemical Substances Bureau"
Project Title:
Evaluation Project of Construction Quality Management of the Sanitary Landfill
Project Subject:
The main objective of this project is to evaluate the construction quality and operation management
Project Year:
2006
Organizer:
Bureau of Environmental Inspection
Project Title:
The project for background investigation of environmental distribution of chemical substances and an
Project Subject:
The major aims of this project were to (1) investigate distribution of concerned chemicals in fiftee
Project Year:
2019
Organizer:
Toxic and Chemical Substances Bureau
Project Title:
The project for the improvement of preventing management and response mechanism of the air pollution
Project Subject:
This project was undertaken to investigate an approach to evaluate the risk potential of hazard or o
Project Year:
2009
Organizer:
Department of Air Quality Protection & Noise Control
Project Title:
Project for Guideline of Chemical Substances Alternatives Assessment in Taiwan
Project Subject:
The project investigates the regulations, operating standards and institutional framework of foreign
Project Year:
2018
Organizer:
Toxic and Chemical Substances Bureau
Project Title:
0800-085-717 toll-free resource recycling service hotline project
Project Subject:
During the two-year project implementation period, the resource recycling 0800 service hotline recei
Project Year:
2006
Organizer:
Recycling Fund Management Board
Project Title:
A project for reviewing the system of recycling, cleanup and disposal of ELV, and surveying the sol
Project Subject:
The project including 36 schemes is categorized in six parts as follow: (1) investigate
and analyze
Project Year:
2006
Organizer:
Recycling Fund Management Board
Project Title:
Project for Assisting the Exeutive Agencies of This Country in Reinforcing Resource Recycling in 200
Project Subject:
“Project for Assisting the Exeutive Agencies of This Country in Reinforcing Resource Recycling in 20
Project Year:
2006
Organizer:
Recycling Fund Management Board
Project Title:
Project Subject:
The plan had been singed in 21, Apr, 2009. It was executed for 8 1/3 months in 21, Apr to 31, Dec. T
Project Year:
2009
Organizer:
Environmental Protection Bureau, Chiayi City
Project Title:
Project on Reduction of Dioxin Emission for Small and Medium Types of Incinerators in Solid Waste, A
Project Subject:
(A) Buildup of the databank for small and medium types of incinerators: 330 stands
(B) Project item
Project Year:
2002
Organizer:
Department of Air Quality Protection & Noise Control
Project Title:
Economy-wide Analysis of Greenhouse Gases Reduction Strategies Using Macroeconomic Models
Project Subject:
TAIGEM-D and GTEM-Taiwan, both developed by the Center for Sustainable Development at the National T
Project Year:
2002
Organizer:
Department of Air Quality Protection & Noise Control
Project Title:
Promote fluorinated gases emission reduction
Project Subject:
The requirements for the management of high green house potential gases(PFCs, HFCs and SF6) has grad
Project Year:
2004
Organizer:
Department of Air Quality Protection & Noise Control
Project Title:
“Proposal for the outline of promoting image rebuilding effort for recycling business in 2010”
Project Subject:
1.object
(1)To establish demonstration about logistics Resource Recycling, strengthen and enrich ben
Project Year:
2010
Organizer:
Recycling Fund Management Board
Project Title:
"The Project for Reviewing Toxicological and Eco-toxicological Information of the Chemical Substance
Project Subject:
"The project period spans from 4th February to 30th November, 2021. The main tasks are to provide te
Project Year:
2021
Organizer:
"Toxic and Chemical Substances Bureau"
Project Title:
Revision business for Facility standard of Recycle waste storage and Management Regulation for Reimb
Project Subject:
In order to implement resource recycle and manage the recycle and
treatment organizations more effec
Project Year:
2006
Organizer:
Recycling Fund Management Board
Project Title:
109 Kinmen County Poison and Chemical Substance Source Verification Management Plan
Project Subject:
In response to chemical substance advocacy this year, A total of six awareness campaigns and two foo
Project Year:
2020
Organizer:
Environmental Protection Bureau, Kinmen County
Project Title:
Using read-across approach to assess the hazardous properties of UVCBs: A preliminary project
Project Subject:
In recent years, our government has facilitated the local version of “Registration, Evaluation, Auth
Project Year:
2021
Organizer:
Toxic and Chemical Substances Bureau
Project Title:
2019 Study and Safety evaluation of Environmental Agents Regulations
Project Subject:
Four implementation tasks were included in this project, including management regulation assessment,
Project Year:
2019
Organizer:
Toxic and Chemical Substances Bureau
Project Title:
Waste Reduction and Recycling Project of Yi Lan County 2004
Project Subject:
For the puspose of increasing recycling rate of Yi Lan County, Yi Lan Environmental Protection Burea
Project Year:
2004
Organizer:
Environmental Protection Bureau of Yi-Lan County
Project Title:
"Project for analyzing and investigating Chemicals at postmarket"
Project Subject:
"This project focuses on four aspects, including usage survey and baseline data study of toxic and c
Project Year:
2021
Organizer:
"Toxic and Chemical Substances Bureau"
Project Title:
Promotion of the Toxic Chemical Substances Institutions and Flow Tracking Management Project
Project Subject:
This year the project has focused on the following six main aspects:
Scheme plan: Establish relevant
Project Year:
2012
Organizer:
Department of Environmental Sanitation & Toxic Substance Management
行政院環境保護署 的其他資料集
核能四廠環評監督委員會會議紀錄
不定期更新更新,52陳先生 | 04-2252-1718#51207 | 2023-08-09 01:04:33
行政院環境保護署非甲烷碳氫化合物(NMHC)監測小時值
每1日更新,196陳先生 | 02-2311-7722#2386 | 2023-08-02 00:58:33
行政院環境保護署縣市(高雄市)小時值-每小時
每小時更新更新,188謝小姐 | 02-2311-7722#2386 | 2022-01-14 01:01:08
行政院環境保護署行政院環境保護署環境檢驗所法定預算
每1年更新,79莊小姐 | 03-4915818#3003 | 2023-08-09 01:05:46
行政院環境保護署變更內容對照表專案小組初審會議紀錄
不定期更新更新,109劉先生 | 02-23117722#2743 | 2022-01-15 01:12:37
行政院環境保護署
公民營廢棄物乙級清除機構許可資料
每月更新更新,176何先生 | 02-2311-7722#2653 | 2022-01-14 01:25:57
行政院環境保護署降雨逕流非點源污染最佳管理技術(BMPs)指引
不定期更新,72林先生 | 02-2311-7722#2811 | 2022-01-15 01:13:03
行政院環境保護署使用中機動車輛噪音檢驗之場所表
不定期更新更新,50謝先生 | 02-23712121#6403 | 2023-08-07 01:02:18
行政院環境保護署全國一般廢棄物產生量
每1月更新,181顏先生 | 02-23117722#2109 | 2023-07-27 01:01:24
行政院環境保護署環境檢驗測定機構許可資料
每1月更新,223楊先生 | (03)491-5818轉2103 | 2023-07-27 01:01:42
行政院環境保護署
各月份場址更新率統計報表
不定期更新更新,202賴小姐 | 02-2383-2389#8102 | 2022-01-15 01:12:17
行政院環境保護署水庫水質監測資料
不定期更新更新,148郭先生 | 2311-7722#2399 | 2023-08-07 01:02:05
行政院環境保護署全國一般廢棄物處理量
每月更新更新,134謝小姐 | 02-23117722#2103 | 2022-01-14 01:21:11
行政院環境保護署空氣品質指標(AQI)
每小時更新更新,93謝小姐 | 02-2311-7722#2386 | 2022-01-12 01:04:49
行政院環境保護署縣市(直轄市)小時值-每小時
每小時更新更新,191謝小姐 | 02-2311-7722#2386 | 2022-01-14 01:00:23
行政院環境保護署
特殊空品測站位置圖
不定期更新更新,159謝小姐 | 02-2311-7722#2386 | 2022-01-15 01:16:08
行政院環境保護署光化測站(潮州)小時值資料
不定期更新更新,236陳先生 | 02-2311-7722#2386 | 2023-08-07 01:03:31
行政院環境保護署公告應回收項目之責任業者申報營業量或進口量年總量資料
每年更新更新,51廖小姐 | 02-2370-5888#3103 | 2022-01-14 01:26:09
行政院環境保護署持久性有機污染物斯德哥爾摩公約國家實施計畫成果報告
每年更新更新,52劉小姐 | 23257399#55531 | 2022-01-15 01:10:06
行政院環境保護署病媒防治業地理資料
不定期更新更新,48薛先生 | 02-2325-7399#55413 | 2023-07-27 01:02:56
行政院環境保護署
固定污染源設置、變更、操作許可申請家數統計
每3月更新,98江先生 | 02-23117722#6201 | 2023-08-03 01:03:09
行政院環境保護署已公告之飲用水取水口一定距離一覽表
不定期更新更新,139黃先生 | 02-23117722#2881 | 2023-07-27 01:02:59
行政院環境保護署水庫水質監測點基本資料
不定期更新更新,175郭先生 | 2311-7722#2399 | 2023-08-07 00:59:33
行政院環境保護署新竹市水量水質自動監測連線傳輸監測紀錄值即時資料集
不定期更新更新,58許先生 | 02-2311-7722#2831 | 2022-01-18 01:24:43
行政院環境保護署特殊性工業區即時監測值資料檔 (氣象監測項目)
每小時更新更新,150丁先生 | 02-2371-2121#6101 | 2022-01-14 01:04:58
行政院環境保護署
行政院環境保護署環境保護人員訓練所法定預算
每1年更新,51陳先生 | 03-4020789#580 | 2023-08-09 01:05:49
行政院環境保護署全國場址新增列管及解列統計表
不定期更新更新,149賴小姐 | 02-2383-2389#8102 | 2022-01-15 01:12:12
行政院環境保護署營建署事業廢棄物再利用機構資料
不定期更新更新,127李小姐 | 02-2311-7722#2633 | 2022-01-14 01:26:14
行政院環境保護署EPQSummary_WasteManagement
不定期更新更新,237郭先生 | 02-2311-7722 EXT.2399 | 2022-01-15 01:13:53
行政院環境保護署空氣品質小時值_高雄市_小港站
每1時更新,382陳先生 | 02-2311-7722#2386 | 2023-08-02 00:57:37
行政院環境保護署